Approved Bond Projects

After careful review of a variety of reports and studies (which can be found on the Facts & Figures page), the Long-Range Facility Planning Committee provided the PSD Board of Education with a set of recommendations for it to consider as it prepares for the future of Pendleton schools. The Board then directed a Facility Advisory Panel to review these recommendations. Below are the recommendations the LRFPC made to the Board. The Board has directed the PSD to ask voters to consider a General Obligation Bond on the November 2013 ballot to fund these projects.*

*NOTE: Costs listed to fund these projects are estimates and are subject to change.

School Potential Scope of Work Approx. Cost
Lincoln Primary Convert to District Offices & Maintenance Shop. $650,000
McKay Creek ES Convert to grades 1-5. Replace roof. Improve safety & security. Improve energy efficiencies. $1,580,000
Sherwood Heights ES Replace existing facility with new school for grades 1-5 with capacity of 528 students. $17,000,000
Washington ES Replace existing facility with new school for grades 1-5 with capacity of 528 students. $17,000,000
West Hills Intermediate Convert to Alt. School. Improve safety & security. Improve energy efficiencies. $1,200,000
Sunridge MS Energy-saving upgrades & add air conditioning. Improve safety & security. $2,045,000
Pendleton HS Fix roof. Energy-saving lighting & HVAC upgrades. Upgrade auditorium seating & stage lighting/sound system. Improve safety & security. Upgrade track/football area with ADA access, ADA bathrooms, improved lighting & improved seating. $5,000,000
Hawthorne Convert to Early Childhood Center. Improve safety & security. Improve energy efficiencies. Relocate District Office to allow for off-street parking & off-street bus loop & drop-off areas. $8,500,000
Total For All Schools $52,975,000

Design Concepts for Replacement Buildings

Sherwood Heights Elementary Design Concept (pdf)

Washington Elementary Design Concept (pdf)

Hawthorne Building (Early Childhood/Kindergarten Center) Design Concept (pdf)

Preliminary Schedule For Potential Bond Projects

This schedule outlines when bond projects -- if approved by voters -- would be completed following the November 2013 election. Click here to see the preliminary schedule.* (pdf)

*Please note that this schedule is subject to change.